    FIDIC Glossary

    Plain-English definitions of the FIDIC terms our consultants reference most often on Saudi projects. Each entry cites the typical clause reference.

    Bill of Quantities (BOQ)

    Clause -

    Itemised list of works with measured quantities and rates, forming the basis of the Contract Price under remeasurement contracts.

    Defects Notification Period (DNP)

    Clause 1.1.3.7

    The period during which the Contractor remains liable to complete outstanding work and remedy defects, as stated in the Particular Conditions.

    Engineer

    Clause 1.1.2.4

    The party named in the Contract appointed by the Employer to administer the Contract and exercise the powers ascribed to the Engineer under the FIDIC conditions.

    Extension of Time (EOT)

    Clause 8.4

    Additional time granted to the Contractor for completion when delay arises from causes for which the Employer bears risk under the Contract.

    Force Majeure

    Clause 19.1

    An exceptional event or circumstance beyond a party's control which could not reasonably have been provided against, avoided or overcome.

    Interim Payment Certificate (IPC)

    Clause 14.6

    A certificate issued by the Engineer stating the amount due to the Contractor in respect of an interim payment.

    Notice of Claim

    Clause 20.1

    A written notice given by a party (typically the Contractor) under Sub-Clause 20.1, describing the event giving rise to the claim, served within 28 days of awareness.

    Particular Conditions

    Clause 1.1.1.5

    The contract document that amends and supplements the General Conditions, tailored to the specific project.

    Provisional Sum

    Clause 13.5

    A sum included in the Contract and so designated for the execution of any part of the Works or the supply of goods, materials, plant or services, used only as directed.

    Taking-Over Certificate

    Clause 10.1

    Certificate issued by the Engineer when the Works are substantially complete and have passed any specified tests, marking the start of the DNP.

    Time-Bar

    Clause 20.1

    Contractual provision that extinguishes a party's entitlement to a claim if notice is not served within the prescribed period.

    Variation

    Clause 13

    Any change to the Works which the Engineer instructs or approves as a variation in accordance with Clause 13.